WC1587869 corresponds to the order for carrying out the works designed under WC1167084 to replace the RO plant concrete tank. The work will include the following:
- Supply and install a new temporary 50m3 tank complete with all peripheral pipelines to be used for the operation of the RO Plant during the construction works.
- Carry out all necessary electrical works including the installation of sensors and accessories on the new temporary storage tank to enable the automatic operation of the RO Plant during the works.
- Remove all redundant pipelines. Secure all pipelines and services that will remain in service. Demolish the existing old concrete water storage tank with approximate dimensions 19 X 22 X 2.5m
- Carry out the works for the construction of the concrete bases of the 2 No. cylindrical GLS Tanks (Capacity 219m3 each).
- Carry out the works for erecting the 2 No cylindrical GLS Tanks with the following dimensions: Diameter 9.3m and Height 3.4m, including 100mm insulation.
- Supply and install all necessary peripheral pipelines of the tanks including the installation of a new UV system.
- Carry out all necessary electrical works including the installation of sensors and accessories on the new GLS Tanks to enable the automatic operation of the RO Plant.
- Test and commission all mechanical and electrical systems and ensure the correct operation of the RO plant.
Project restrictions expected for this project:
- Persons entering the area of the works should have a valid security pass. Such pass can only be provided to Greek Cypriots, Turkish Cypriots or UK nationals.
- The operation of the RO plant should be maintained unaffected throughout the construction period.
The Provisional Key Tender dates for the project are as follows:
- Expression of interest: 22/12/2025
- Expression of interest return: 9/1/2026
- Invitation to Tender: 15/1/2026
- Tender Return Date: 19/2/2026
- Contract award: 27/3/2026
- Commencement of work: 30/3/2026
- Completion of work: 9/10/2026
The currency of this project is Euro (โฌ).
The location of this project is Ayios Nikolaos, Cyprus (British Forces).
Recommended Comments
Join the conversation
You can post now and register later. If you have an account, sign in now to post with your account.