Description
1. Overview
The works comprise the supply and installation of steel sheet piling to support temporary and permanent structures across the A66 NTP Project, BBA Section 3b.
2. Detailed Scope
2.1 Supply of Materials
The Contractor shall supply:
โข Steel sheet piles in various profile sizes, complete with corrosion protection and cut to length requirements.
2.2 Installation of Sheet Piles
The Contractor shall undertake:
โข Pile installation works including driving, vibration, pre drilling, cutting, interlock connections, tie rods, waling and bracing systems.
โข Removal of sheet piles upon completion of works.
2.3 Associated Works
The Contractor shall complete associated activities including:
โข Pile guide frames
โข Dewatering screens
โข Structural support components
2.4 Pre Construction & Site Activities
Activities include:
โข Mobilisation and site establishment
โข Setting out
โข QA testing
โข Preparation of record drawings and certification
2.5 Coordination Requirements
The Contractor shall coordinate with related project disciplines including foundations, drainage and earthworks teams.
________________________________________
3. Standards & Compliance
All works must be carried out in accordance with:
โข BD 21/01
โข National Highways Specification
โข Relevant BS/EN/Eurocode standards
โข CDM Regulations
________________________________________
4. Key Supplier Requirements
The Contractor must:
โข Demonstrate capability to manage CDM and SHES risks
โข Provide method statements, vibration and noise mitigation plans
โข Coordinate closely with Temporary Works Designers
โข Collaborate with the Balfour Beatty site and engineering teams
โข Submit all required QA documentation, including testing and certification evidence
________________________________________
5. Procurement & Delivery Model (Informational Context Only)
A competitive tender process will be conducted to select a single supply and install partner for consistency, scalability and value.
(You can exclude this section if you only need the technical scope.)
________________________________________
6. Risks & Mitigation - Contractor Responsibilities
The Contractor shall support risk management in areas including:
โข Early award and resource confirmation to reduce over commitment risks
โข Managing vibration and settlement risks through pre condition surveys and real time monitoring
โข Mitigating design or construction clashes through integrated design reviews and 3D coordination
โข Minimising traffic management delays via advanced planning and flexible work slots
โข Managing steel/fuel cost volatility through early procurement and index linked pricing mechanisms
________________________________________
7. Deliverables
The Contractor shall provide:
โข Complete installation of specified sheet piling works
โข Full QA documentation including test results and certification
โข As built / record drawings